IATI Identifier: NL-KVK-83517626-ORIO10KE21
In the Wajir district 96 percent of the population does not have access to clean drinking water. The main objective of the project is making clean water available to Wajir towns on a continuous basis in order to decrease the vulnerability to droughts of its inhabitants and their cattle. The project is defined as the design construction and operation of a new water supply system to serve Wajir and Habaswein towns, Lagbogol centre and the surrounding communities. The potable water will be made available by pumping groundwater from the Merti aquifier which is approximately 110 km from Wajir. The project consists of:- Drilling developing and equipping boreholes, - Provision of clean water pumping equipment and storage facilities,- Construction of main(pipeline) from Habaswein to Wajir town,- Development of power generating system for pumping,- Construction of reticulation system for Habaswein and Wajir towns,- Standpipes and the connection of existing standpipes to the new water supply.
more_horizBasic drinking water supply
| Name | Type | Role |
|---|---|---|
| BAM International B.V. | Private Sector in Provider Country | Implementing |
| Ministry of State for Land Development of Northern | Local Government | Implementing |
| Ministry of Finance (MOF) | Local Government | Implementing |
| Invest International | Private Sector | Accountable |
| Invest International | Private Sector | Funding |
| Transaction Value |
Provider
Receiver |
Type | Date |
|---|---|---|---|
| 47,884 EUR (Valued at Dec 21, 2015) | Provider N/A BAM International B.V. | Disbursement |
date_range
Dec 21, 2015
|
| -16,909 EUR (Valued at Dec 17, 2015) | Provider N/A Receiver N/A | Incoming Funds |
date_range
Dec 17, 2015
|
| -16,909 EUR (Valued at Dec 17, 2015) | Provider N/A Receiver N/A | Commitment |
date_range
Dec 17, 2015
|
| 95,467 EUR (Valued at Jun 19, 2013) | Provider N/A BAM International B.V. | Disbursement |
date_range
Jun 19, 2013
|
| 45,108 EUR (Valued at Nov 09, 2012) | Provider N/A BAM International B.V. | Disbursement |
date_range
Nov 09, 2012
|
| 26,579 EUR (Valued at Sep 21, 2012) | Provider N/A BAM International B.V. | Disbursement |
date_range
Sep 21, 2012
|
| 59,013 EUR (Valued at May 25, 2012) | Provider N/A BAM International B.V. | Disbursement |
date_range
May 25, 2012
|
| 290,959 EUR (Valued at Nov 21, 2011) | Provider N/A Receiver N/A | Commitment |
date_range
Nov 21, 2011
|
| 290,959 EUR (Valued at Nov 21, 2011) | Provider N/A Receiver N/A | Incoming Funds |
date_range
Nov 21, 2011
|