SIHA Network
room Naguru
arrow_back See all Activities

Sudan We Cannot Wait

IATI Identifier: UG-NGO-1317-SudanWCW

Published on IATI
  • date_range Jan 01, 2021 - Dec 31, 2025
  • autorenew Implementation (Status)

Consortium partners and grassroots women and activists have increased capacity to track progress of gender transformative programs.

more_horiz
Sectors:
  • Women's equality organisations and institutions

Participating Organisations

SIHA Network Regional NGO Accountable
Netherlands - Ministry of Foreign Affairs Government Funding
SIHA-Sudan National NGO Implementing

Transaction

Transaction Value Provider
Receiver
Type Date
17,426 EUR Sudan 2022 overhead costs from January to December 2022 overhead costs from January to December Expenditure
date_range Dec 31, 2022
70,317 EUR 2022 Direct staff costs from January to December for Sudan 2022 Direct staff costs from January to December Expenditure
date_range Dec 31, 2022
275,612 EUR 2022 Activity, travel, project office, investment and equipment, monitoring, evaluation and auditing costs for Sudan 2022 Activity, travel, project office, investment and equipment, monitoring, evaluation and auditing costs Expenditure
date_range Dec 31, 2022
254,452 EUR Provider N/A Receiver N/A Incoming Funds
date_range Jan 01, 2022
7,357 EUR Provider N/A Receiver N/A Expenditure
date_range Dec 31, 2021
105,433 EUR Provider N/A Receiver N/A Expenditure
date_range Dec 31, 2021
1,202,265 EUR SIHA Regional SIHA Sudan
date_range Jan 01, 2021
256,193 EUR Provider N/A Receiver N/A Incoming Funds
date_range Jan 01, 2021

Budget

291,329 USD
  • 256,193 EUR (Valued at Dec 31, 2021)
    date_range Jan 01, 2021 - Dec 31, 2021
access_time Updated on Jun 27, 2023 11:48:57